Abu Dhabi Food Hub Fireproofing Project in Abu Dhabi, UAE

Abu Dhabi Food Hub fireproofing in KEZAD Area B, Abu Dhabi: Ibtikar applied Nullifire SC804 Intumescent Paints to 120,820 m² of structural steel, achieving a 120-minute fire rating. Completed January 2026.

Abu Dhabi Food Hub – fire protection project by Ibtikar Fire Proofing

Project Type Intumescent Paints

LocationKEZAD Area B

Area120,820 m²

Fire Rating120-minute

MaterialNullifire SC804

CompletionJanuary 2026

Project Overview

The Abu Dhabi Food Hub fireproofing project is located in KEZAD Area B, Abu Dhabi, UAE, where Ibtikar delivered professional structural steel fireproofing and passive fire protection solutions for Abu Dhabi Food Hub. Covering approximately 120,820 m² of steelwork, the project was completed in January 2026 using Intumescent Paints with Nullifire SC804, spray-applied to provide reliable protection in accordance with the specified 120-minute fire-resistance requirement.

Ibtikar’s scope included the application of the fireproofing system to primary and secondary structural steel members such as columns, beams, connections, and other critical steelwork. Our team strictly managed surface preparation, primer compatibility, coating application, and dry film thickness (DFT) verification at every stage. All fireproofing activities were executed in accordance with approved project requirements, manufacturer recommendations, and applicable UAE passive fire protection and Civil Defence requirements.

Through controlled application and systematic quality inspections, Ibtikar delivered a durable, fully compliant, and properly documented fireproofing system engineered to preserve the structural integrity of the building during fire exposure.

Explore more Ibtikar projects or contact our team to learn about our structural steel fireproofing, intumescent coating, and passive fire protection services across the UAE and GCC.

Location: KEZAD Area B
Project Date: January 2026
Project Type:Intumescent Paints
Surface Area: 120,820 m²
Fire Rating: 120-minute
Material “INTUMESCENT”:Nullifire SC804
Material “CEMENTITIOUS”:Southwest Type 5GP
Application Method: Spray Fireproofing

Fireproofing Scope & Application

  • Structural Steel Protection

    Primary and secondary structural steel members — columns, beams and connections — are protected against fire exposure to maintain load-bearing capacity for the required fire-resistance period, in line with the project's passive fire protection strategy.

  • Intumescent Coating Application

    A reactive intumescent coating system is applied to prepared steel surfaces. Under fire exposure, the coating expands to form an insulating char layer that slows the rate of heat transfer to the substrate, delaying loss of structural strength.

  • Quality Control & Inspection

    Dry film thickness (DFT) is measured throughout application against the specified coating build-up. Each stage is documented with inspection records, culminating in a final walk-through and sign-off prior to handover.

Fire Protection System

A layered coating system builds up fire resistance on the steel substrate. Products and film thicknesses are project-specific — see the technical documents below.

  1. Layer 01

    Steel substrate

    Prepared structural steel, cleaned and profiled to the specified surface standard prior to coating.

  2. Layer 02

    Primer

    A compatible primer system protects the substrate and provides adhesion for the intumescent coating. Thickness per specification.

  3. Layer 03

    Intumescent coating

    The reactive fireproofing coating, applied to the dry film thickness specified for the project's required fire-resistance rating, from 60 up to 120 minutes. Under fire exposure it expands to form an insulating char layer.

  4. Layer 04

    Topcoat

    A protective topcoat is applied where specified, for UV resistance, weathering or a decorative finish.

Each layer depends on the one beneath it — primer adhesion determines how well the intumescent coating bonds to the steel, and the specified dry film thickness is what delivers the certified fire-resistance rating. Products and film thicknesses are project-specific: always confirm against the data sheets and the approved project specification before application.

Project Execution

  1. Stage 01

    Surface preparation

    • Steel surfaces cleaned and prepared to the standard the coating system requires
    • Preparation signed off before any coating is applied, so the system bonds correctly
  2. Stage 02

    Primer inspection

    • Primer film thickness and coverage checked across the steelwork
    • Intumescent application only proceeds once the primer passes
  3. Stage 03

    Intumescent application

    • Applied in controlled passes to build up the specified dry film thickness
    • Spray, brush or roller to suit the product and the site conditions
  4. Stage 04

    DFT inspection and handover

    • Dry film thickness measured at multiple points on each member and recorded against the project specification
    • Final joint inspection on completion, with documentation compiled and issued for handover and close-out

Surface preparation and primer sign-off come first for a reason — an intumescent coating applied over contaminated or incorrectly primed steel can fail to adhere, and that is found out long after the steel has been closed in. The DFT records are the evidence: the fire-resistance rating is only as good as the film thickness actually achieved on each member, which is why the readings are taken point by point and kept with the handover file.

Project Results

120,820 m²Protected Area

120-minuteRequired Fire Rating

Intumescent Paints Coating System

CompletedProject Status

Approved 100%Inspection Status

Project Gallery

Fire Proofing Material

Nullifire SC804 | Water-Based Intumescent Coating for On-Site Application

BS 476 & Certifire CF5929 Certified Passive Fire Protection for Structural Steelwork. High-build formulation optimized for 90-minute fire resistance, with a limited 120-minute option available.

Nullifire SC804 intumescent coating for structural steel
Fire Resistance Rating Optimised 90 Min (120 Min Limited)
Volume Solids 69% ± 3%
Density / Specific Gravity 1.38 ± 0.02 kg/L
Coverage (Theoretical) 1,000 g/m² @ 0.5 mm DFT
Max Wet Film Thickness (WFT) 1.0 mm/coat spray, 0.6 mm brush
VOC Content < 0.1 g/L (Ultra-Low VOC)
Application Method Airless Spray or Brush/Roller
Pack Size & Storage 25 kg Drums (Protect from Frost)

Source: Nullifire SC804 Technical Data Sheet (Tremco CPG). Rating is optimised for 90 minutes — the 120-minute figure is a limited option, not the primary rating. No single max-DFT figure is published, so coverage is shown at its theoretical reference thickness instead.

Substrate Preparation

  • Steel Preparation: Apply only onto a clean, undamaged, dry, primed steel surface free from contaminants.
  • Substrate Restrictions: Use only primer systems approved per Nullifire's guidance for this product.

Primer Systems

  • Consult Nullifire for the current approved primer list for SC804.

Airless Spray Application Setup

  • Operating Pressure: 2500–3000 psi (175–210 kg/cm²)
  • Tip Size: 17 to 21 thou
  • Fan Angle: 20°–40°
  • Fluid Line: 10 mm ID

Drying Schedule (at 20°C)

Dry Time @ 0.2mm WFT 2 Hours
Dry Time @ 0.5mm WFT 3 Hours
Dry Time @ 1.0mm WFT 4 Hours

Recommended overcoat time is 16 hours. Drying times also vary by temperature (e.g. 1.0mm WFT takes 6h at 10°C, 3h at 30°C) — the figures above are the 20°C reference column.

Third-Party Certifications & Compliance

  • Tested to BS 476: Part 20/21.
  • Certifire Approval CF5929.
  • ETAG 018 — approved up to Y exposure without topcoat.

Technical Documents

Fire Proofing Material

Carbothane 137HS | High-Build Polyurethane Protective Topcoat

Fast-Drying Two-Component Coating for Direct-to-Metal Application in C1–C3 Environments. Outstanding UV and Gloss Retention for Long-Term Exterior Performance.

Carboline Carbothane 137HS polyurethane topcoat
Fire Resistance Rating N/A — Protective Topcoat
Recommended Environment C1–C3 (No Primer), C4–C5 (With Primer)
UV / Gloss Performance Outstanding UV & Gloss Retention
VOC Content 328 g/L (Part A, as supplied)
Volume Solids Refer to manufacturer's TDS
Max Dry Film Thickness (DFT) Refer to manufacturer's TDS
Application Method Refer to manufacturer's TDS
Pack Size & Storage Refer to manufacturer's TDS

Sources: Carboline product page (environment, UV/gloss) and the Carbothane 137HS Part A Safety Data Sheet (VOC content).

Substrate Preparation

  • Corrosivity Category: Suitable for direct-to-metal application in C1–C3 environments without a primer.
  • Higher Corrosivity: For C4–C5 environments, apply over an appropriate Carboline primer system.

Primer Systems

  • Confirm the approved primer system with Carboline for your substrate and corrosivity category.

Application

  • Two-component polyurethane, mixed per Carboline's stated ratio before application.
  • Formulated for fast-drying, high-build application with excellent dry times relative to standard polyurethane topcoats.

Drying Schedule

Tack-free, recoat and full-cure times vary with temperature and humidity. Refer to the Carboline Technical Data Sheet for exact figures.

Third-Party Certifications & Compliance

  • As a topcoat, Carbothane 137HS is typically used as part of a certified fireproofing system rather than certified on its own. Confirm with Carboline if a specific approval is required for your project.

Technical Documents

Fire Proofing Material

Southwest Type 5GP | General-Purpose Cementitious Fireproofing

Up to 4-Hour Fire Protection Across 100+ UL Designs. Lightweight spray-applied formula with a rapid 15–20 minute recoat option using Accelerator A-20.

Southwest Type 5GP cementitious spray fireproofing
Fire Resistance Rating Up to 4 Hours (100+ UL Designs)
Nominal Density 15 lb/ft³ (240 kg/m³), ASTM E605
Compressive Strength 3,700 psf (177 kPa), ASTM E761
Bond Strength >200 psf, ASTM E736
Max Thickness Per Pass 3/4" (19 mm)
Application Method Machine-Applied Spray
Pack Size & Storage 50 lb (22.7 kg) Bags
VOC Content Refer to manufacturer's TDS

Source: Southwest Type 5GP Product Data Sheet (Carboline/Southwest Fireproofing). Type 5GP is the general-purpose grade of the Type 5 family, formulated as a lower-density, standard-purpose alternative to Type 5MD.

Substrate Preparation

  • Steel Preparation: All substrates must be clean and free of loose scale, dirt, oil, grease, condensation, or any other substance that would impair adhesion.

Primer Systems

  • Primers are not required or recommended for most applications. Optional bonding agents are available for specific site conditions — confirm with Southwest/Carboline against your project's UL design number.

Mixing & Application

  • Water Ratio: 8–10 US gallons (30.3–37.8 L) per 50 lb (22.7 kg) bag
  • Mixing: Approx. 2 minutes at 40 RPM
  • Initial Pass: 1/2"–5/8" (12.7–15.9 mm)
  • Subsequent Passes: 3/4" (19 mm) or less per pass

Drying Schedule

Dry to Recoat (Standard) 4 Hours @ 77°F (25°C)
Dry to Recoat (With Accelerator A-20) 15–20 Minutes

The Accelerator A-20 option is a distinguishing feature of Type 5GP for fast-turnaround schedules. Figures are at 77°F (25°C) — confirm with Southwest/Carboline for other site conditions.

Third-Party Certifications & Compliance

  • Tested to UL 263 / ASTM E119, with 100+ UL designs across floor/ceiling, beam/joist, roof/ceiling, column and wall assemblies.
  • Additional standards: ASTM E136, E384, E605, E736, E759, E760, E761, E84, E859, E937, G21.
  • AWCI Technical Manual 12-A compliant.

Technical Documents

Why Choose Ibtikar

  • UAE project experience

    A track record of fireproofing delivered across the UAE's industrial, commercial and infrastructure sectors.

  • Specialised fireproofing expertise

    Dedicated focus on passive fire protection and intumescent coating systems for structural steel.

  • Professional quality control

    Documented dry film thickness inspection and quality checks at every stage, issued as a signed inspection report.

  • Technical and project support

    Technical guidance from specification and system selection through to inspection, handover and authority submission.

Frequently Asked Questions

This project used a Nullifire SC804 intumescent coating system, specified to deliver a 120-minute fire-resistance rating on exposed structural steel.

Steel is first cleaned and primed, then the intumescent coating is applied in controlled passes — by spray, brush or roller depending on the product and site conditions — to build up the specified dry film thickness.

The required rating is set by the project’s fire strategy and applicable building regulations, based on factors such as building use, height and occupancy. This determines the fire-resistance period the steelwork must achieve.

DFT is measured using a calibrated gauge at multiple points across each member and recorded against the thickness specified for the required fire rating, with results documented for inspection.

Coating thickness depends on the steel member’s section factor (Hp/A), the required fire-resistance period, and the specific product’s certified performance data.