About Residential Tower G+8 Dubai Investment

In July 2023, Ibtikar Fire Proofing completed 26,000 m² of fire protection on the structural steel of Residential Tower G+8, Dubai Investments in Dubai Investments Park, Dubai, using Carboline Pyrolite 15 cementitious fireproofing.

With 26,000 m² of steel across a G+8 residential tower, the project called for a high-output cementitious system that could be sprayed quickly and economically floor by floor. The coating was applied by our trained crews to the manufacturer’s specification and verified with dry film thickness checks before handover to the main contractor.

Carboline Pyrolite 15

Fire Proofing Materiel: Carboline Pyrolite 15

Pyrolite 15 A 15 lbs./ft³ density SFRM intended for the fire protection of interior structural columns, beams, joists, decks, walls, roofs, girders, floors and pre-cast concrete units. It is tested and certified for fire resistance ratings up to 4 hours.

Download

Features

  • Durable cementitious formulation
  • Noncombustible
  • Can be injected with Accelerator A-20 for fast set and increased yield (optional)
  • Asbestos-free – complies with EPA and OSHA regulations.

Benefits

  • Mineral Wool free – no airborne fibers.
  • Styrene free – no toxic decomposition gases.
  • Economical – Maintains project on budget.
  • Design flexibility with over 40 UL designs.